• Switch OFF the BTS cabinet and disconnect Abis connectors from DDF before offline start • Disconnect the Abis connector from The DDF • Switch ON the BTS cabinet breakers and connect the Laptop with BTS • User Name COMMTE Password COMMTE • Communication Port setting • OR • After connecting this window will be appear • Go to Configuration-> BTS-SW Download-> to download BTS software • After BTS-SW download this window will appear • Go to offline Files and select First File of Master File. • Go to offline Files and select First File of DDL file. • Click ok to start downloading SW • BTS software starts to download. • All these Files are downloaded • Go to Configuration BTS commissioning • Click start commissioning • Edit Qmux Address • Edit sector Mapping • Check All Twin TREs. • Click End Commissioning Click • All modules Shifted to update modules.

• Click No to end • Reconnect the Abis connector at DDF by verifying the TX/RX cables properly • Give Hard Reset to BTS cabinet as the OML has established to put the site on Downloading. • OFF Line Commissioning Completed Successfully. • BTS ON-Line commissioning Procedure using B10 Go to configuration>> Hardware setting>>Begin HW modification • Go to configuration> BTS commissioning Go to start commissioning> Edit Q1 Address, Edit Sector Mapping and Twin TRA setting as in offline.

Jan 25, 2018 - BTS ON-Line commissioning Procedure using B10 Go to configuration>> Hardware setting>>Begin HW modification. Edit Sector Mapping.

• Go to configuration> Hardware setting>End Modification to end online commissioning • Online commissioning steps Connect the Abis connector at DDF by verifying Tx/Rx cable properly. OML will be established after primary Abis has connected to DDF. Give hard reset to BTS after OML has established.

Put site on Downloading from OMC. O&M will be established as downloading completes. Billie holiday the complete commodore recordings rar download. Connect Laptop to BTS MMI port.

Go to configuration>Hardware setting>Begin Hardware modification. • Online commissioning steps Go to configuration>BTS commissioning>start commissioning. Edit Qmux Address Edit sector mapping Check all Twin TRA setting. Click end commissioning and shift all modules from selected modules to available modules.

Go to configuration>Hardware setting>End Hardware modification. Click yes when an automatically hardware modification window appears. Hw Audit will be run and all Hardware will be shown after sometime. • ON Line Commissioning Completed Successfully. • Software components combiner Fan Unit Tres clock Alarm card Hardware Shown in software window • Alarms window • Transceivers Shown in window • Transceivers Types Four type of Transceivers in Alcatel Equipment TRAGE>Gsm Single TRE TRADE>Dcs single TRE TGT09>Gsm Twin TRE TGT18>DCS Twin TRE TAGHE>High power TRE • VSWR Shown in window • Sectors Shown In window • Station units • BSC SBLs (security block levels) BTS OM & Sectors.Sec RSLs can be unlock from local Terminal. • Troubleshooting If a TRE or combiner is in Not Operational or FOS state then disable it then initialize it by using init command.

If TRE or combiner can not operational by doing above command then remove it by using the following method. Go to configuration>>Hardware setting>>Begin HW modification. Go to Configuration>>Hardware setting>>Remove.

Remove the Hardware from BTS. Window will be appear of Hardware removal, select the module to remove. Go to Configuration>>Hardware setting>>End Modification. Click yes when configuration changes window appears. • Hardware Removal Method Step:1 • Hardware Removal Step:2 • Hardware Removal Step:3 • Troubleshooting cont.

When a module goes in FOS state then it must be disable by using disable command before initializing it by using init command otherwise it will not goes to operational state. When a module is in Not Operational state with color white then it means it has not got its RSL number still.